Summary
The ditch paving project is running 64% complete against 73% of the time elapsed, and the contract grew by $88,750 to $2,225,272.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Mar 3, 2026.
Impact analysis
Contract increased $88,750 to $2,225,272.
Residents near the Lateral B-1 drainage ditch who get improved drainage infrastructure.
Mentions & discussions (2)
City Council - Mar 3, 2026
The contractor on the city's main drainage improvement project has demobilized to work on other jobs, leaving the project 64 percent complete against 78 percent of the schedule elapsed. The city attorney is researching options including a bonding company claim.
City Council - Jan 20, 2026
The ditch paving project is running 64% complete against 73% of the time elapsed, and the contract grew by $88,750 to $2,225,272.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Bossier City
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.