Emergency sewer repairs on Voss Drive and Central Park lift station
The city had to fix a collapsed sewer main and a failed manhole on an emergency basis, spending nearly $389,000 combined from the sewer contingency fund.
Utility worker pay incentives
Water and wastewater operators will now earn real certification pay ($0.50–$2.25/hour) plus monthly CDL bonuses, aimed at keeping qualified staff running the city's water systems.
Golden Meadows Drive storm drain replacement
Crews are replacing a failing box culvert and storm drain near Bayou Drive; the road should be passable by end of day with repaving to follow.
Heather Lane sewer main failure
A 24-inch sewer force main blew out along Viking Drive and cost $17,387.70 to fix. The council declared an emergency to pay for it from sewer capital contingency funds.
Fuel Station Conversion Change Order
Only one bid came in for converting city fuel stations — $1.58 million against a $1.15 million estimate — so the council took it under advisement.
Two new public utilities positions
The council green-lit filling a Utility Worker in the Lift Stations Division and a full-time Animal Control Officer, both with backfill authority.
Lampkin-Burdine Sewer Main Emergency Repair Funding
The council adopted emergency ordinances to pay for a water main blowout at Hospital Drive and a failed sewer main on Lampkin Street — fixing infrastructure that failed during the recent freeze.
Recurring sewer repairs at Lampkin and Burdine streets
The city paid $98,572.25 for emergency repairs there and introduced an ordinance adding $226,398.55 more to finish the job — a sign of aging infrastructure.
Water and sewer utility financial strain
Net operating income in the water/sewer fund is down sharply — 79% in February versus last year. Council asked when it stabilizes; part of it is an accounting reclassification of over $1 million from capital to operating, and summer chemical costs will rise.
Bardot Drainage Basin project costs
Construction costs have risen above the $2.3 million state watershed grant, so the council signed off on an updated commitment letter covering the roughly $370,000 gap.